Lack of IT expertise still a 'major risk' for government projects

But apparently the OGC's gateway reviews have reduced risk of failureÂ…

By Andy McCue, 5 November 2004 08:03

NEWS Red- and green-light 'gateway' reviews are addressing the government's poor record of delivering major IT projects but the lack of in-house IT and project management expertise is still a "major risk", according to a report by parliamentary watchdog the National Audit Office (NAO).

The report, Improving IT Procurement, examines the effectiveness of the Office of Government Commerce (OGC) since it was set up to tackle a track record of over-budget and delayed public sector IT projects by monitoring, reviewing and recommending best practice on individual projects as they progress from business case to delivery.

Central government IT spend in 2003 totalled £2.3bn and since 2001 the OGC has operated six-stage 'gateway reviews' using a red-, amber- and green-light system for recommending whether IT projects should proceed to the next stage of the procurement process.

Of the 254 IT-enabled projects given a Gateway Review rating between June 2002 and March 2004, 50 per cent of them were rated as amber, where key issues need addressing, 28 per cent red, indicating immediate action needed and 22 per cent were green, indicating satisfactory progress.

Reviews are minimising the risk of IT failure and changing departmental and supplier behaviour for the better. But too many IT projects are entering the review process too late and leaving it too early, warned the report.

"A major risk, however, is that projects are entering the process too late - that is at Gates 2 and 3 (crucially, after the business case has been prepared), and exiting the process too early - that is before Gate 5 (when an assessment of the continuing need for the service, value for money and contract management arrangements can be made)," the report said.

There NAO report also warns of a continuing lack of appropriate project and programme management skills and experience, which present a "major risk to the successful delivery of IT-enabled projects".

The shortage of IT and contract management skills and insufficient involvement from senior managers was highlighted in 76 per cent of OGC Gateway reviews, followed by the need for better risk management and criteria to benchmark the success of a project in 54 per cent of reviews.

Sir John Bourn, head of the NAO, said in the report: "Government departments have a chequered history in the handling of IT-enabled projects and programmes. OGC has made significant strides in identifying reasons for past failureÂ… These remain, however, early days and my report makes recommendations to build on these foundations in order to reduce the likelihood of future failure."

Comments

There are 6 comments. Join the discussion

  1. 1. anonymous

    Lack of IT expertise still a 'major risk' for government projects

    Of course as all IT pros are now re training as hairdressers.

  2. 2. anonymous

    Government project - what about the contract.

    As a 'Tester' on a project, I complained that I could not sign off 'deliveries' as I could not obtain documentation describing the users needs, and the processes 'programmed' to fulfil those requirements.
    When, eventually, the complaint was finally put to senior management levels -
    The reply from the developer was that they would not supply the documents as they were not included in the 'preliminary work' contract.
    And no contract for the actual system had been signed.
    The project got canned after (by my estimate) over 90% of the work had been done, and 80% of the probable cost had paid for on a 'time & labour' basis.

    That highlighted a major failing of 'Government' projects - the lack of perceived need, or perhaps just politically aware unwillingness of senior management to wholeheartedly commit themselves to a project.

  3. 3. Roger Huffadine

    Biometric ID cards are dead in the water then - that is when the project gets reviewed by someone with IT knowledge and no vested interest.

  4. 4. anonymous

    All Tony Blair's roads lead to nowhere, but it's still a long journey!

  5. 5. Robin Street

    Many government IT related projects require security clearance. As an experienced IT related project and business change manager I'm finding it increasingly difficult to apply for work as I no longer have a current clearence having taken a role that didn't need one. Clearence requirements are becoming a bar to working in Government. Not because I'm a risk but because I don't have a current clearence and no one will wait while I'm cleared.

  6. 6. Steve Metzler

    Perhaps it is time to re-think the dependence that the government and their contractors have on "professional Project Management certification" and instead look to employ people who actually accomplish difficult projects. Standards are a good thing, but in this industry broad experience, developed personal skills, and proven dedication to quality produce better and less costly products. But try telling that to the recruiters out there looking for project managers.

Post your comment

In order to post a comment you need to be registered and logged in.

Log in or create your silicon.com account below

Will not be displayed with your comment

By signing up for this service, you indicate that you agree to our Terms and Conditions and have read and understood our Privacy Policy.

Questions about membership? Find the answers in the Membership FAQ