The Department of Health (DoH) must turn around the multibillion pound Care Records Service within six months or risk seeing the scheme broken up, according to MPs.

The rollout of the Care Records Service (CRS), a project to link up medical records at English hospitals, is now years behind schedule. Currently, the patient administration systems (PAS) needed to lay the groundwork for electronic medical record transfers are only deployed in 133 of England's 380 acute hospital trusts.

A report released today by the parliamentary spending watchdog, the Public Accounts Committee (PAC), labelled the DoH's progress on the CRS rollout as "very disappointing" and said its 2014-15 completion date - already four years later than originally planned - is now in doubt.

Unless the deployment of the CRS "improves appreciably" over the next six months the DoH should consider pulling the plug on the planned national rollout, according to the PAC.

Instead, the PAC recommends the DoH should consider allowing trusts to apply for money to buy their own electronic medical records systems.

PAC member Conservative MP Richard Bacon told silicon.com it is time to dump the centralised rollout of CRS.

"The national rollout of care records is a naïve and oversimplistic distraction from getting a detailed local care record services going.

"The local service providers are never going to deliver what is required - power and the vast majority of money left in the pot needs to be returned to the local hospital trusts," he said.

Technical problems and delays have affected the two software systems that will be used to run the CRS - Cerner and Lorenzo. By the end of 2008, iSoft's Lorenzo care records software had not gone live throughout a single acute hospital trust and several London hospitals reported difficulties in running the Cerner Millennium system.

Interim PAS systems are being provided to trusts in the North, Midlands and East while they wait for the Lorenzo CRS to be rolled out - which will need replacing again when Lorenzo is ready for deployment.

The majority of the 133 PAS' rolled out so far will need further upgrades before they are able to handle full electronic medical records.

The rollout of the CRS to acute hospital trusts is among the biggest of the 10 IT projects that make up the £12.7bn National Programme for IT (NPfIT).

Difficulties with PAS rollouts have been compounded by the decision by Accenture and Fujitsu to walk away from the NPfIT, leaving only CSC and BT as the two main suppliers for the programme. Accenture and Fujitsu had previously been rolling out PAS systems to hospital trusts.

Doctors' union the British Medical Association (BMA) urged caution on NPfIT spending in the wake of the review.

Dr Vivienne Nathanson, head of science and ethics at the BMA, said in a statement: "With the UK deep in recession the government must ensure that Connecting for Health confronts the lessons of the past - the NHS IT project can't be paid for with a blank cheque.

"Trusts must have more freedom to implement IT systems that take into account their local needs."

In a statement, the DoH played down the PAC's criticisms.

"We welcome the report. New IT systems in the NHS are delivering better, safer and faster care," it said.

Comments

There are 4 comments. Join the discussion

  1. 1. anonymous

    NHS NPfIT

    1. Poorly Scoped
    2. Little buy in from end users, as ignored at stage 1
    3. Over-funded
    4. Programme Managed and Procured to death
    5. £20bn down the toilet this time ?

    The mother of all Government IT Runaway Trainwrecks is steaming in.....and will arrive in 6 months.

  2. 2. Tony Shoebridge

    The centralised, monolithic architecture not only ran counter to modern localised, web design, but ignored what had been learnt by other pioneers of elctronic records management in the NHS.

    Five years after the start of this inauspicious programme, I had a heart attack. After six month's treatment, my local hospital and GP have no proper records of me, only sub standard hand written notes. I give doctors/nurses a verbal briefing every time I meet them and relie on my diary for recent stats and details of drugs. There are no records of blood tests - four sets have been lost! And I end up with no-one knowing what's really up with me!

  3. 3. drew stephenson

    Out of curiosity, how long will public bodies get away with just dismissing investigation results? It's a tactic that appeared to develop during the Blair years but appears to be alive and well still. Don't like the results of an audit? Just dismiss them! No need to enter into debate or provide any evidence, just trot out the same old mantras and all the bad numbers will just disappear.
    Why do we (and the media who receive these statements) continue to accept them?

  4. 4. anonymous

    If the NHS IT system is dropped I sincerely hope that those responsible in our mickey-mouse NHS management will loose their jobs! Like everything else the UK government does, it is a complete fiasco, but they will find some excuse for the mess.

Post your comment

In order to post a comment you need to be registered and logged in.

Log in or create your silicon.com account below

Will not be displayed with your comment

By signing up for this service, you indicate that you agree to our Terms and Conditions and have read and understood our Privacy Policy.

Questions about membership? Find the answers in the Membership FAQ