MPs probe £900m overspend on late submarines

CAD problems partly to blame

Tags: submarine, mod

By Dan Ilett

Published: 15 March 2006 12:45 GMT

The government has again been forced to admit that failures in a Computer Aided Design (CAD) program have contributed to the delay of the build of three nuclear submarines and to the project coming in £900m over budget.

Adam Ingram, a minister for the Ministry of Defence (MoD), said on Monday that the CAD system chosen to design the submarines was not up to scratch, after Lib Dem Mike Hancock quizzed him over why there had been delays.

In a written statement, Ingram said: "The increase in costs and delay to the delivery of the Astute programme stem primarily from problems that arose from the application of CAD techniques. Due to the complexity of the programme, the benefits that CAD was envisaged to provide were more difficult to realise than either [the] MoD or the contractor had assumed."

BAE Systems, which is contracted to build the Astute-class nuclear submarines, renegotiated the contract in 2003 when it realised the CAD system was not suitable for the job.

This is the second time the MoD has had to answer for overspending on this submarine project, after facing MPs on the House of Commons public accounts committee last year.

A number of factors caused the cost of the project to rise from £2.57bn to £3.49bn, according to the MoD.

An MoD spokesman told silicon.com: "The programme ran into problems. That was because of design issues, poor management and the use of CAD. [We] and the contractor overestimated [CAD] and underestimated the problems it would cause.

"We had to learn lessons from similar things in the US on subs. We had to renegotiate the contract. Not all of it is down to CAD but that was an element."

The first of the submarines is set to enter service in 2009, when Swiftsure and Trafalgar-class submarines will start to be replaced.

BAE said it will take no profit in 2006 for the Astute contract; the company is this year bidding for a contract to build a fourth submarine.

A spokeswoman for BAE told silicon.com: "There are no new delays. We recognised the system should never have been taken on. But it was a large defence contract and a must-win."

  1. Zones
  2. Management
  3. Networks
  4. Software
  5. IT Services
  6. Hardware
  1. Verticals
  2. Public Sector
  3. Financial Services
  4. Retail & Leisure

silicon.com Public Sector
Get the latest public sector news straight to your inbox. Sign up for the PS newsletter today!


  • Jobs
Bristol/Chief Mechanical Engineer/50K-60K/Defence/Nuclear

Bristol/Chief Mechanical Engineer/50K-60K/Defence/Nucleur This position is held in the highest regard within the company in terms of technical ...

Bristol/ Drawing and Model Checker/35K-40K/Defence/Nuclear

Bristol/ Drawing and Model Checker/35K-40K/Defence/Nuclear You will be working in teams, designing such complex products as Submarine Weapon Handling ...

Lead FPGA Designer

My MOD / Defence related Client is urgently recruiting for a team of FPGA Designers and a Lead. This is working in a Defence / MOD environment, ...

Nick Heath
Let's shine a light into the public sector IT money pit
With £16bn being spent, why is productivity still falling?

Tim Ferguson
BBC is taking tech seriously, so give it a break!
Auntie is the envy of the world but doesn't get the credit it deserves at home...

Peter Cochrane
Peter Cochrane's Blog: Open info for all?
Government stonewalling citizens

Nick Heath
Home Office CIO on taming tech and why ID cards are good news
Interview: Annette Vernon, Home Office CIO

Nick Heath
NHS records, Google and Microsoft: Where do you want your data?
Politicians: Heal thyself

Alan Hunt
NHS network: Time to get secure
Patient data in need of a check up

Agenda Setters 2009
Welcome to the ninth annual Agenda Setters poll – silicon.com's list of the top 50 most influential individuals in the technology and IT industries, from techies and CIOs to entrepreneurs and business leaders. Find out more in our latest special report.




Quick Sitemap Links: